Intersection Work to Begin!

WCC have advised the construction work at the Village intersection will start Monday 14 June.

Key points to note:

  • Hours of work will generally by Monday - Friday, 7am - 5pm, with some occasional weekend work.

  • Construction will take approximately 3 months.

  • There will be no access to the East side of Waitoa Road from the intersection. Alternative routes will be clearly sign posted. (Please note, WCC are now aware a detour via Arcus Way is not suitable as per their letter. Do not use Arcus Way as a thoroughfare as it is a one way, private road and is largely gravel).

  • Number 35 and 14 Bus Routes will e detoured via Waipapa Rd, Hataitai Rd, William St and Tapiri St.

  • A project board will be placed in the village to keep us all informed with progress.

Link to Letter from WCC with more details.

Details on planned parking

More details on the project can be found here on the WCC website.

If you have any questions or concerns, you can contact Stephen Harte, Transport Project Manager, 04 499 4444 or email transport@wcc.govt.nz